The NJ BPU Develops Proposed Rules for the State’s Long-Term Solar Successor Program

On July 9, 2021, Governor Murphy signed Assembly Bill A4554, which directs the New Jersey Board of Public Utilities (BPU) to establish within one year a long-term successor solar renewable energy certificate program to replace New Jersey’s existing Transition Incentive Program, also known as the TREC program.

Board of Public Utilities Develops Proposed Rules

Even in advance of this legislation, however, the BPU was making plans for the successor solar program. A public meeting to discuss two Orders that would, within 30 days of issuance, announce new parameters for the new program and close the existing program, is scheduled for 10:00 a.m., Thursday, July 28.

The BPU has also announced plans to publish proposed rules in the New Jersey Register, most likely on August 2 or August 16. A draft of these proposed rules is available on their website here. The rules would establish a Successor Solar Incentive Program, which the BPU is referring to as “SuSI.” Rulemaking is potentially significant because it is a multi-month process, providing 60 days for comments (until October, assuming publication occurs in August), a final adoption that is required to address all the comments, and republication. This process might last well into December of this year.

New Jersey Long-Term Solar Successor Program

As we noted in our previous blog post, “NJ BPU Extends the Deadline for Completing TREC Projects, but Remains Silent as to Timing of a Successor Program,” a BPU Order was entered on June 24, granting a blanket six-month extension to complete projects already in the pipeline of the TREC program. But it appears from the Proposed Rules, together with the expected BPU Order closing the TREC program as of (presumably) August 27, that developers may not be able to register new projects until the new “portal” is opened; and that cannot take place until after the rulemaking process is finished.

Therefore, the delay between the closure of the TREC program and the opening of a portal for new projects could well result in a build-up of proposed projects that will come flooding into the BPU all at one time. Because there will be an annual cap on eligible SuSI projects (the “megawatt block”), and the portal will close every year when the cap is reached, the SuSI program may be guaranteed to fall short every year if this is indeed the case.

We hope to hear more about these latest developments and the plans for new TREC projects at the BPU’s July 28 meeting, and we will continue to monitor these developments. Meanwhile, if you have any questions about the existing TREC program or related public utilities or solar energy matters, please feel free to contact us at jlaskey@norris-law.com or lmiller@norris-law.com.

Share
Related Posts
New Jersey BPU Adopts New Incentives for Solar Projects
NJ BPU Extends the Deadline for Completing TREC Projects, but Remains Silent as to Timing of a Successor Program
Transitioning from the Transition: Questions Abound Regarding the New Jersey Successor Solar Program
James H. Laskey
Member
James H. Laskey
Visit Profile
Related Posts
New Jersey BPU Adopts New Incentives for Solar Projects
NJ BPU Extends the Deadline for Completing TREC Projects, but Remains Silent as to Timing of a Successor Program
Transitioning from the Transition: Questions Abound Regarding the New Jersey Successor Solar Program
Share
Join our growing team
We are looking for quality attorneys to help us do more for our clients. At Norris McLaughlin, each attorney has the same opportunity to succeed whether you’re at the beginning of a career or pinnacle of the profession.
Subscribe to our content
Receive timely legal information
delivered to your inbox
Subscribe to our content
Receive timely legal information
delivered to your inbox
© 2021, Norris McLaughlin, P.A., All Rights Reserved. Attorney Advertising.
Meritas

We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume you consent to our cookie policy. Learn more